There we go, and now we're recorded, so now we really can be official.
00:00:06
The first item on the agenda is call to order and reading the notice of electronic meeting, which we will not be doing because we're meeting in person.
00:00:16
We do, however, have one voting member who has to be appearing by video.
00:00:23
As I understand the protocol under the statute, we have to vote on whether to allow Stacy to participate remotely.
00:00:33
So we have a motion.
00:00:36
First of all, Stacy, where are you and why can't you be here?
SPEAKER_04
00:00:41
I don't want to make you jealous.
00:00:42
I'm in the Outer Banks.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:00:44
OK. And I assume that's vacation rather than work.
SPEAKER_04
00:00:50
It is.
00:00:51
It is.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:00:52
I was going to say it was work.
00:00:54
I want your job.
SPEAKER_04
00:00:55
Exactly.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:00:58
Do we have a motion to allow her to participate remotely from Ms. Malek?
00:01:02
Is there a second?
00:01:03
Second.
00:01:04
Okay, all in favor say aye.
00:01:06
Aye.
00:01:06
All opposed?
00:01:08
Congratulations.
00:01:09
You have been approved to participate remotely.
00:01:13
Is there anything else we need to call to order?
00:01:15
Do we need to have a formal role taken?
00:01:17
Is that what's next?
00:01:19
We know we've got Ms. Londrey approved.
Christine Jacobs
Non-Voting Member, MPO Policy Board
00:01:22
Yep.
00:01:23
And we know Sean Nelson is going to be out.
00:01:25
Lloyd Snook?
Lloyd Snook
Vice-Chair, MPO Policy Board
00:01:26
I'm here.
Christine Jacobs
Non-Voting Member, MPO Policy Board
00:01:27
Brian Pinkston?
Lloyd Snook
Vice-Chair, MPO Policy Board
00:01:28
Here.
Christine Jacobs
Non-Voting Member, MPO Policy Board
00:01:29
Mr. Galloway, you know will not be here.
00:01:31
Ms. Malek.
00:01:32
Yes.
00:01:33
And then non-voting Mr. Rieck.
00:01:36
Eddie Shackelford, we know is still out.
00:01:38
Ms. Monteith.
SPEAKER_07
00:01:39
Here.
Christine Jacobs
Non-Voting Member, MPO Policy Board
00:01:41
Mr. Williams.
00:01:43
Here.
00:01:44
I broke down first names.
00:01:45
That was a bad move.
00:01:48
What?
00:01:49
Here.
00:01:49
Richard.
00:01:51
Duran.
00:01:51
FHWA.
00:01:53
Brian Long.
00:01:55
Lee Kondor.
00:01:58
So we have our role.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:02:14
Next up is Matters from the Public.
00:02:18
3 minutes per speaker.
00:02:20
The public are welcome to provide comment on any transportation related topic, including the items listed on the agenda and or to comment during items that have been marked with a star.
00:02:33
There are a few that have been marked with a star.
00:02:35
But in any event, is there anybody in the public, either here or remotely, who wishes to address us?
SPEAKER_07
00:02:46
I thought you said something.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:02:48
Somebody just said they like our hybrid set.
Christine Jacobs
Non-Voting Member, MPO Policy Board
00:02:52
Not seeing any hands raised online.
00:02:54
If you are joining us remotely and want to have a comment, please raise your hand using the Zoom raise your hand feature.
SPEAKER_07
00:03:01
Brian, is there anybody in the chat trying to get up?
Christine Jacobs
Non-Voting Member, MPO Policy Board
00:03:06
Yeah, I've got one to comment about.
00:03:08
Whoa, I like the hybrid setup.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:03:11
OK, so I guess we have no matters from the public.
00:03:15
General administration, first item is review and acceptance of the agenda.
00:03:20
We've already deviated from the agenda by eliminating the reading of the notice of electronic meeting.
00:03:25
Other than that, any other changes or corrections to the agenda?
00:03:32
We have a motion to approve the agenda.
Brian Pinkston
Member, MPO Policy Board
00:03:36
I move that we approve the agenda.
00:03:38
Second.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:03:39
All in favor say aye.
00:03:41
Aye.
00:03:42
All opposed?
00:03:43
Aye.
00:03:45
Okay.
00:03:45
Carried unanimously.
00:03:47
Next, approval of the May 25th, 2022 meeting minutes.
00:03:53
Any changes, corrections, additions?
SPEAKER_07
00:03:59
I move the second for a minute.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:04:01
There's a motion.
00:04:02
Do we have a second for that motion?
00:04:04
Second.
00:04:06
All in favor say aye.
00:04:08
Aye.
00:04:09
All opposed?
00:04:10
Motion carries.
00:04:12
So we have rather quickly gotten to the meat of the meeting, the federal transportation grant opportunities.
00:04:18
Mr. Mickles, do you want to present?
SPEAKER_11
00:04:21
Sure, Mayor Snook.
00:04:23
This evening we have Mr. Bill Kirus, Executive Director for the Association of Metropolitan Planning Organizations.
00:04:32
He's here along with his colleague, Mr. Ty'Von Njorgen, and they are here to talk about IIJA, something that the Policy Board and the Committee
00:04:44
That's okay.
00:04:53
That's all right.
SPEAKER_00
00:04:56
It's certainly not the first time and it won't be the last.
00:05:01
So, well, thank you.
00:05:02
As Ryan mentioned, my name is Bill Caruso and I serve as executive director of the Association of Metropolitan Planning Organizations.
00:05:10
And with me is my colleague, Levon Boyajian, who serves as our policy advisor.
00:05:14
So I just wanted to thank Christine, Sandy, and Ryan for inviting us to participate today.
00:05:20
We appreciate the opportunity to be here and I apologize we weren't able to make it down in person, but we'll do our best to present virtually.
00:05:29
We have a presentation today to walk through the IIJA to include some of the grant opportunities that were a part of the bill.
00:05:40
We'd like to try to keep this as much discussion-based as possible.
00:05:44
So we certainly have a lot of content that we're going to present today, but please feel free to stop us at any point, ask any questions, ask us to dive into something a little bit deeper.
00:05:54
Hopefully there'll be a few minutes at the end for some Q&A, but certainly feel free to interrupt us at any point to slow down or answer any questions, dive into something a little bit deeper.
00:06:04
So thank you again for the opportunity and we'll go ahead and dive in.
00:06:10
So Lev, I'll go ahead and turn it over to you.
00:06:11
Lev and I are going to tag team the presentation throughout this afternoon.
SPEAKER_05
00:06:15
Thanks, Bill, and thanks for having us here today.
00:06:19
We've got a number of slides here.
00:06:21
We'll get through most of them fairly quickly.
00:06:24
Some of them are just revisiting what we already know, some of the big picture provisions that have come out of the IIJA and then get into some grants, not too detailed, but at least talk about some of them and then kind of wrap up with what
00:06:44
What the future holds, if you will, in terms of implementation of the bill, a little discussion about appropriations and the elections and what that could mean for the surface transportation bill over the next several years.
00:06:58
So as a recap, after months of trying to get a surface transportation bill, Congress and the president finally did agree on a $567 billion bill.
00:07:10
Over a hundred billion dollars over five years in grant programs.
00:07:15
It's probably closer to 120 or 130, maybe even higher, you know, as you add in some of the research and some of the smaller grants that are out there, but there's a lot.
00:07:25
There's several new formula programs that target a variety of things in the climate change and carbon reduction areas of transportation.
00:07:37
including a heavy investment in electrification.
00:07:40
As you all know, the NEVI program, the plans I believe are due August 1st, which is right around the corner for that program.
00:07:51
And then there's some examples of incentivizing good planning, particularly in the PROTECT program, which is the resiliency program.
00:08:02
that Congress established to address infrastructure that's impacted by climate change and maybe trying to get ahead of some of it.
00:08:10
Next slide.
00:08:14
These are the top line numbers of the modes in the IIJA.
00:08:19
You're all very familiar with contract authority, I assume, out of the Highway Trust Fund.
00:08:24
And then this new category of funding, this guaranteed funding under advanced appropriations, which is new to a surface transportation bill.
00:08:33
But it guarantees $184 billion over the life of the IIJA that
00:08:44
In a really nice twist of things is not subject to the annual appropriations process.
00:08:50
As we get to that slide later on in the presentation, I'll revisit you.
00:08:59
Am I coming through okay, or is there background?
00:09:02
I apologize.
00:09:05
Maybe that's okay.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:09:06
There was a little background there for a second.
00:09:09
Yeah, yes.
00:09:12
Oh, my God.
00:09:12
Okay.
00:09:13
Okay, my bad.
SPEAKER_05
00:09:15
All right, we good?
00:09:16
I want to make sure that you can hear me and understand me.
00:09:21
This is a distribution by mode, just a graphic to give a sense of where Congress decided to invest in the surface transportation bill.
00:09:30
As you know, the IIJ was a much bigger bill that included funding for broadband, water infrastructure, agriculture products, a variety of different things, but obviously we're focusing on the surface transportation side of things.
00:09:45
Next slide.
00:09:48
This is the general split between competitive discretionary programs in the bill, excluding NHTSA and the Federal Motor Carrier Safety Administration.
00:09:58
So this is primarily focused on rail, public transportation, transit, and highways, and some of the research programs.
00:10:07
So
00:10:08
descriptionary programs have grown since the FAST Act.
00:10:13
Again, just giving more opportunity to those eligible applicants to apply for federal dollars.
00:10:19
Next slide.
00:10:22
The next two slides are going to cover some of the administration priorities.
00:10:25
I know you're very familiar with these.
00:10:27
The president and USDOT has,
00:10:31
been very forthcoming in the policies that the administration would like to address through not only surface transportation and other DOT programs, but across agencies of the federal government.
00:10:47
Equity, transformative projects, safety and climate.
00:10:51
Those are the, I guess the top four, if you will, that we see throughout the notice of funding opportunities in the grant programs.
00:11:01
You know, some of them are not statutory, which I know can cause some uncertainty when applying programs and others successfully address some of these policy priorities.
00:11:18
And how will they weigh on the outcome and the evaluation of an application?
00:11:26
Next slide.
00:11:28
This is a little bit more detailed than some of the priorities of the administration.
00:11:36
I'll draw your attention to the Justice 40 initiative, which again,
00:11:46
is a broad initiative that covers the federal government agency-wide to deliver 40% of the benefits of federal investments to disadvantaged communities.
00:12:02
Climate change, again, these are two particularly large components of the notice of funding opportunities where the USDOT has more control
00:12:13
In collaboration, I want to hit on just briefly, but in many of the webinars that I've listened to, I think Bill would agree, the administration is focusing on a partnership and collaboration between states and local governments
00:12:36
So I think that as potential applicants are looking at some of these grant opportunities, can you build a stronger application by partnering with a broad number of stakeholders?
00:12:54
Which I think, and we'll see soon enough when some of these awards do start coming out,
00:13:01
How highly some of these priorities are reflected in the awards.
00:13:07
So, you know, if you see 50% of the awards going to some sort of a partnership, I think that tells you something.
00:13:13
That maybe next year, applying for RAISE or AMFRA or rural or whatever it might be, if you didn't get an award as maybe a state DOT or maybe as an MPO or local government, maybe there's an opportunity to resubmit with a different flavor
00:13:30
of applicant partnerships.
00:13:34
And I would also stress, if you do apply and you don't get an award, always seek the, I apologize, I apologize, the joys of working at home with the mailman and the dog.
00:13:57
I lost my train of thought.
00:13:58
So anyway, ask for the debrief.
00:14:01
Don't get an award, ask for a debrief.
00:14:03
Ask USDOT why we didn't get it, where was the weakness in our application, how do we make it stronger?
00:14:10
And they're very good about it.
00:14:11
I participated in several debriefs and they're very good.
00:14:17
I think they're very useful too.
SPEAKER_11
00:14:18
Next slide.
SPEAKER_00
00:14:20
And Lev, one thing that I would add that we've continued to hear as well, is there
00:14:26
Looking at these programs and trying to identify ways to address cross or multi-jurisdictional projects as well.
00:14:33
And that's part of the reason why they're pushing the collaboration and joint applications so hard.
SPEAKER_05
00:14:42
Next slide.
00:14:45
This is a real kind of high-level look at some of the things that are in the IIJA in terms of requirements, programs, and policies that may be a little permissive or are permissive and then some of the programs
00:15:01
The IIJA MPOs make policy changes on board representation, not significantly to the point that anybody here should get too excited about.
00:15:14
Stronger coordination, some additional planning factors, additional participation from interested parties, and then an emphasis on complete streets.
00:15:25
as it pertains to PL funding, which we'll get into a little bit in the next several slides.
00:15:33
Housing is a big issue, and it's linked to transportation and how to plan a little bit more closely between the two areas.
00:15:43
Protect, again, I mentioned it earlier, there's a resiliency plan that you can do.
00:15:49
There are benefits to doing it.
00:15:51
But you don't have to do it as an MPO.
00:15:54
And then there's a broader use of social media.
00:15:58
It was an issue that many of you probably experienced during the pandemic where you had to take alternative measures to be able to accomplish some of the requirements that MPOs are required to do.
00:16:14
Also allowing interested parties to communicate a little bit better or maybe more effectively.
00:16:21
And then under the programs, like I mentioned, the carbon reduction program is formula and sub allocates 60% of the funds, protect is a formula, discretionary, EV charging and bridge are also both formula and discretionary to these new programs.
00:16:40
Next slide.
00:16:43
This is a specific direction to USDOT for the Secretary to update the regulations with regard to the planning and fiscal constraint to clearly define that beyond the
00:17:14
To ensure that the outer four years of the plan are defined as beyond the first four years.
00:17:23
During our conversations, putting together the AMPO recommendations, there was a good discussion about how closely the outer years of a plan could impact the tip and the earlier years in terms of moving money around
00:17:43
You know, if a state initiative had created more opportunity with more funding, then you move those funds around from the outer years to those tip years.
00:18:00
So this is something that the Senate bill in particular addressed to provide a little bit more fiscal flexibility.
00:18:10
We do expect this to be more fleshed out in a comprehensive planning rule that we are expecting to be noticed in the Federal Register early next year.
00:18:26
So that planning rule will be more broad than just this issue, we suspect, or at least we're getting some signals.
00:18:35
from USDOT.
00:18:37
But I thought it was important to point this one out just because Congress was very specific about this.
00:18:42
Next slide.
00:18:45
Here's some amendments to Section 134, which is the section of Title 23 that houses the Metropolitan Transportation Planning.
00:18:57
When designating for the first time, they want the MBO to consider
00:19:02
the equitable and proportional representation on the board based on population of the metropolitan planning area.
00:19:10
The House and Senate bills were different on this.
00:19:12
I believe the House bill said ensure
00:19:18
and Proportional Representation, the Senate Select Consider, which is a lower bar, it's a requirement to consider, that's why it's on this slide, but it's not a mandate in terms of how you designate your board membership.
00:19:34
Congress just wants you to consider when designating for the first time.
00:19:39
Again, this is the coordination piece.
00:19:42
This pertains to MPOs in the same urbanized areas.
00:19:46
Congress wants stronger coordination, particularly in the use of data.
00:19:54
When these MPOs are put together, they're planning matters, but it does not require a joint
00:20:03
A joint tip or a joint plan.
00:20:08
They just want the MPOs in these same urbanized areas to be using data that's consistent because they feel like that's a stronger way to reflect the larger area, if you will.
00:20:23
Some planning factors.
00:20:26
Housing is a new planning factor.
00:20:27
As many of you know, there's a long list of planning factors that MPOs are required to look at when they're putting together
00:20:37
Their plans.
00:20:39
And then participation by interested parties.
00:20:41
Again, this is going at the housing policy that the administration wants to more strongly coordinate with transportation.
00:20:54
So they would like the MPOs to at least talk to affordable housing organizations when they're putting together the plan and the tip.
00:21:04
Next slide.
00:21:08
This is a funding requirement for complete streets.
00:21:12
This is a specific section in the IIJA that requires a 2.5% investment in complete street standards or policies.
00:21:27
The states have a similar requirement
00:21:31
But there is an opt-out if you can demonstrate to the Secretary that you have these types of policies and standards in place.
00:21:41
We did a very brief verbal survey in Florida a few months ago during the AMPO Tech
00:21:49
Symposium.
00:21:51
And we understand at this point that USDOT is very flexible in terms of how you meet these complete street requirements.
00:22:01
And in fact, in most cases, MPOs were exceeding this 2.5% of PL funds.
00:22:09
So we're always interested in hearing from your division regional
00:22:16
Offices, or if you've even had contact with regard to this particular provision in the IIJA.
00:22:25
Next slide.
00:22:28
Surface Transportation Block Grant Program Consultation.
00:22:32
This is a new one.
00:22:34
They amended the Surface Transportation Program Consultation for
00:22:45
Non-TMA goes in the state to establish a consultative process to describe how surface transportation block grant funds would be allocated in the areas, the non-TMA areas, during the life of the bill.
00:23:03
As you know, TMAs do have a specific suballocation amount that they can more or less rely on.
00:23:11
Non-TMAs don't.
00:23:14
And we heard from a lot of long TMEs during the development of AMPO's policy positions.
00:23:23
And there were some stronger suggestions, but this is what Congress eventually decided to go with.
SPEAKER_10
00:23:33
And we'd be interested to know how this is working in Virginia.
SPEAKER_05
00:23:43
So please let us know.
00:23:44
And if you have questions or comments about this, we're happy to try to walk through this a little bit more.
00:23:51
We can take it offline on a different call.
00:23:54
Next slide.
00:23:57
Some additional provisions that I thought were worth mentioning.
00:24:01
You can develop a housing coordination process plan, not a requirement.
00:24:05
This is one of those permissive policy provisions in the IIJA.
00:24:10
It only applies to the TMAs.
00:24:14
Keep in mind things that are permissive in one bill and become requirements in the next bill.
00:24:24
So this is something that AMPO will want to hear from, hear about over the next several years.
00:24:35
Just to kind of get a heads up and have a story, if you will, that we can tell Congress how much MPOs may be doing this.
00:24:46
And there may not necessarily be a need for Congress to make it more.
00:24:51
But again, it's an opportunity if you want at the TMA level.
00:24:56
I mentioned the social media and other web-based tools earlier.
00:25:00
And then a resiliency improvement plan.
00:25:03
This is under the new program.
00:25:07
There's opportunities to receive a higher federal share, up to 90% on projects.
00:25:14
If, and this works for the state as well as for those who develop our resiliency improvement plan.
00:25:22
On the one hand, you can get an increase of, well, I have a negative 7%.
00:25:25
Your local share would decrease by 7% if the rip is developed and a priority project is on tip.
00:25:32
You can get an additional 3% off of the non-federal share if the rip is incorporated into the plan.
00:25:43
I would love to tell you more about this, but we don't have any guidance yet from USTOT.
00:25:50
We are expecting August, Bill, if I remember correctly, some guidance on the
00:25:59
on the PROTECT program because, as I mentioned earlier, there's a formula component, so a portion that's already going out to the states, and then there's a grant program that will provide grants for planning and construction to address resiliency.
00:26:17
So stay tuned.
00:26:19
When we get that guidance, we'll make sure that we post it somewhere on the AMPO website.
00:26:26
Next slide.
00:26:29
I talked a little bit about this earlier.
00:26:31
This new carbon reduction program averages about a billion, two billion, three every year.
00:26:38
Formula program, 65% sub allocated by population.
00:26:43
The same as surface transportation block grants.
00:26:47
There is a requirement to make available to each urbanized area.
00:26:53
Over 50,000, some obligation authority so that you actually have some real money, if you will, to go along with the contract.
00:27:02
So you can do some projects.
00:27:06
And then it does require each state in consultation with the MPO to develop a carbon reduction strategy within two years of when the bill passed, which was what, November last year.
00:27:19
So about a year and a half to develop that reduction strategy and then every four years afterwards.
00:27:28
Next slide.
00:27:31
I mentioned this already, Bill.
00:27:32
I don't think we need to spend too much time on this.
00:27:34
We expect the guidance and the grant program to be coming out hopefully in the next month or two.
00:27:45
I mentioned the bridge program a little bit earlier.
00:27:48
Big focus on bridges, all bridges, all system bridges.
00:27:55
They want to address they being Congress.
00:27:58
And I know that in the states and at the local level, there's a need to address the rehabilitation or the replacement preservation of bridges.
00:28:09
And Congress
00:28:11
I took a large step in that direction.
00:28:13
There's a formula program that's already been apportioned to the states and there's guidance on that.
00:28:20
And the bridge investment program grant program is on the street right now.
00:28:26
I think applications, I think planning applications are due in the next couple of weeks.
00:28:33
Funding that's projects and then other bridge projects.
00:28:38
And then 15% of the apportionment, the formula piece, is set aside for all off-system bridges.
00:28:46
And it's at 100% share.
00:28:48
So good opportunity, at least at the local level, to address all system bridges with 100% federal money.
00:28:56
And that's a five-year program as well.
00:29:00
The National Electric Vehicle Infrastructure Formula Program, NEVI, those funds have gone out.
00:29:07
It is not subject to the obligation limitation that other programs that are funded under the Highway Trust Fund are subject to.
00:29:17
Don't want to go into the formula on what that means, but generally if Congress puts out a billion dollars in formula money from the trust fund, there's usually a haircut that goes along with the obligation limitation.
00:29:32
But because this was advanced appropriations, it's not subject
00:29:37
So it just means more money is available for EV charging infrastructure.
00:29:43
And as I mentioned, maybe it was on another call.
00:29:47
I can't remember now.
00:29:49
The NEVI formula funds cannot be made available for obligation until the states submitted this plan, a NEVI plan, to this joint Office of Energy and Transportation.
00:30:05
and Federal Highways has to approve it.
00:30:08
And these plans are due August 1st.
00:30:09
So what's that, four days, three days, four days, five days?
00:30:14
So I know that the states are working diligently to get those plans to this new joint office.
00:30:25
Next slide.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:30:25
Who in Virginia does that?
SPEAKER_05
00:30:28
It should be the Virginia DOT.
00:30:30
Okay.
00:30:31
I don't know who specifically, but
00:30:34
It's a requirement in the states.
00:30:40
One more time?
00:30:46
Okay.
00:30:48
Collaborate to be competitive.
00:30:49
We mentioned this a little bit earlier.
00:30:53
In terms of some of the programs that MPOs are specifically eligible for, along with many, many others, there's 17 programs that I've identified.
00:31:01
There might be a few more that I missed.
00:31:03
I don't think I did.
00:31:05
Like I said, there's over a hundred billion in discretionary programs over the life of the bill.
00:31:10
There is a USDOT website that many of you may already have bookmarked on your computer that gives you a schedule.
00:31:20
And I think a link to any of the notice of funding opportunities that have been made available.
00:31:25
And then they give an estimated timeline of when the NOFO
00:31:29
will come out yesterday.
00:31:31
FTA just released its All Stations Accessibility Notice of Funding Opportunity.
00:31:37
I think it was a little over $350 million to upgrade legacy stations and systems to make them compliant with the American with Disabilities Act.
00:31:47
So that's the most recent one that I saw.
00:31:49
Bill, I don't know if you saw any more today.
00:31:52
I checked recently, but I haven't seen anything.
00:31:58
Under the combined applications, many of you know that the USDOT has taken a different direction, if you will, on combining three notice of funding opportunities into a single notice of funding opportunity.
00:32:11
They did this with INFRA, the MEGA program, you know, projects, new and rural infrastructure.
00:32:21
which merged them into a single grant program.
00:32:25
I think the intent was to give USDOT more flexibility in how they would award funds.
00:32:32
Because some projects may fit into two programs and it gives them a little bit more discretion.
00:32:37
I would imagine the ultimate discretion on which program to fund a particular project on.
00:32:44
And those applications were due several weeks ago.
00:32:49
And again, as we mentioned, there's an emphasis from the administration on joint applications that are coordinated with locals.
00:32:58
Next slide.
00:33:02
We don't need to spend a lot of time on this.
00:33:04
I think we'll probably give you the slide deck.
00:33:06
This is just we're trying to keep pace with what USDA is doing in terms of when the grants are coming out, when they're due,
00:33:17
We kept it focused primarily on surface transportation.
00:33:21
I don't know if anyone here is glad for an airport terminal program, but those awards have already been made if anybody had applied.
00:33:30
And if you did, you'd probably know if you got one or not.
00:33:32
Next slide.
00:33:35
This is the same slide, different programs.
00:33:41
Again, I think.
00:33:44
There's a link on the USDOT website, and I know that Bill and I probably check that daily, if not twice a day, to see if it's been updated.
00:33:53
Next slide.
SPEAKER_00
00:33:54
And Lev, I don't know if we just wanted to also mention that the Healthy Streets Program and the Active Transportation Infrastructure Investment Program, they're both subject to annual appropriations, and they were not funded in FY 2022, and AMPO
00:34:09
submitted a letter encouraging Congress to consider funding those.
00:34:14
We encourage them to fully fund.
00:34:16
They didn't quite fully fund, but they did kick some funding in for FY23.
00:34:21
So we were happy to see that.
00:34:22
And that's reflected here.
SPEAKER_05
00:34:24
And that'll be something that comes out next year or whenever Congress decides the appropriate process.
00:34:33
But it'll be fiscal year 23, probably calendar year 23.
00:34:36
Excellent.
00:34:40
So these next couple of slides, I think it's three in total, just talk about the grant process and what USDOT is using to evaluate applications and some of the requirements.
00:34:54
And this is just a list.
00:34:57
It's not reflective of every grant, Notice of Funding Opportunity, but it's some of the things that we've seen.
00:35:05
You may have seen yourself if you've applied for grants in the past, but as anybody would do, you know, they post these Notice of Funding opportunities.
00:35:16
If you're interested in these opportunities, it is incumbent, and I know you do it, read them.
00:35:23
There are a lot of applications and forwards and sideways and ask questions and go to the frequently asked question sections on the websites and really understand those opportunities so that you know what you're getting into.
00:35:39
Because there's a lot of information that an applicant needs to collect, needs to be collected, and sometimes you have to go and find it.
00:35:50
Hopefully you don't have to pay for it, but you might have to, but you need a good understanding of what USDOT is looking at in order to get to a highly ranked project that lands on the secretary's desk for his ultimate approval, if you will.
00:36:07
And there are different stages along the way that applications advance.
00:36:13
And so again, these are some of the things that you can take a look at.
00:36:17
that you should think about as you're putting together or pursuing or thinking about pursuing a grant opportunity.
00:36:23
Next slide.
00:36:26
This is a little bit maybe more detailed, if you will.
00:36:30
Again, some of these things are very obvious.
00:36:34
Your environmental is going to be, you know, if you're doing a capital program or capital project, you need to have an environmental done.
00:36:40
Not done, I shouldn't say that.
00:36:42
You need to have a description of where your NEPA is in the process.
00:36:48
If you're just starting a NEPA and you expect a full EIS, you probably want to wait a year or two before you apply for a grant.
00:36:56
If you know you are going to get an EA in the next six months, you can say that in your application.
00:37:02
Just have a good understanding of where you are in the process.
00:37:06
The closer you are to finishing it and getting a ROD or a FONSI or whatever the outcome might be, the better it is for an application.
00:37:13
Obviously, you don't need those for planning.
00:37:18
Again, some of these others are just the requirements that I've seen very common in many of these.
00:37:26
funding opportunities that any applicant should be prepared to address and deal with as they apply for a grant.
00:37:35
Next slide.
00:37:38
Again, more of what to consider.
00:37:41
This is really maybe questions you ask of yourself.
00:37:44
Can you actually write a grant application?
00:37:47
Do you have the bandwidth?
00:37:48
Do you have the personnel?
00:37:49
Do you have to hire outside consultants?
00:37:51
There's a lot out there.
00:37:53
They do good work.
00:37:56
Should you partner with the state?
00:37:57
States have, and I'm not as familiar with Virginia, but I know that they have a lot of
00:38:02
talented people at the Virginia DOT that you may want to work with.
00:38:07
Talk to them about it.
00:38:09
And if you don't and you go solo, can you administer the grant?
00:38:15
Can you actually draw down and spend the money and make that project successful?
00:38:25
These are the things that USDOT is going to look at in your application.
00:38:30
And you really have to demonstrate that you have that capacity because they want to make sure to the extent that they can, federal dollars are invested efficiently, that they address the project in the application.
00:38:47
And then at the end of the day, the money is drawn down eventually.
00:38:51
Next slide.
00:38:55
This jumps a little bit ahead in terms of what we've seen since the IIJA was signed into law and what are the things that are impacting the implementation of it.
00:39:10
The first one there is a slow rollout of guidance and grants.
00:39:14
This is not a knock on USDOT.
00:39:17
I said this yesterday.
00:39:18
It's just that there's a lot.
00:39:22
So many more new grant programs.
00:39:24
There's four new formula programs.
00:39:26
There's a lot out there on their plate.
00:39:29
And they're doing the best they can, in my opinion, just my personal opinion.
00:39:35
But it's slow, but they're doing what they can.
00:39:39
Inflation.
00:39:41
You know, when the bill was signed into law, prior to the bill being signed into law, Congress was touting how big it was, the biggest infusion of federal dollars in the nation's history.
00:39:51
Then along came Mr. Inflation and started eating up some of those, some of those increases in funding, if you will.
00:40:02
It's still the largest increase, but you know, things
00:40:06
construction costs are increasing, material and labor costs, transportation costs, there's labor shortages.
00:40:17
You know, some states are doing gas tax holidays.
00:40:22
I don't know if all states use their gas tax for infrastructure to fund their capital or not, but it could be an impact in terms of now the available resources, if you will, primarily on the local match side.
00:40:37
We've heard supply chain disruptions for the last couple years.
00:40:42
I hope they get them worked out soon, but it's still an impact to getting construction projects, construction broadly.
00:40:50
And then we've heard lastly here, not lastly, but one of the things that came up from the MPO community was the Buy America changes and escalating costs under Buy America.
00:41:01
The IIJA went beyond what we typically have in America to build in America and manufacture in America.
00:41:09
And as a result of that, it's costing projects potentially or increasing costs on projects.
00:41:19
I don't have the data to support it, but this is some of the things that I've heard from other associations, as well as members within the APO community.
00:41:30
Next slide.
00:41:32
We popped this up here because it's relatively new and it's another potential requirement on MPOs.
00:41:41
You move forward with a new performance measure specifically to establish declining CO2 targets, establish a method
00:41:53
More measurement and reporting from help of emissions in the transportation sector.
00:42:01
USDOT did one I think back in 2017 and then it was repealed in 2018.
00:42:05
This is another go at a performance measure for GHG.
00:42:13
I encourage you to read the notice of proposed rulemaking
00:42:19
It does not require, would not mandate a level of targets, but you have to have declining targets.
00:42:27
I did not read any sort of a punishment for failure to meet a declining target.
00:42:34
We're in the process now of developing ample comments internally within the organization with the help from people membership.
00:42:45
We will be submitting comments.
00:42:47
They're due by October 13th, which may seem like a ways, as we all know, these dates have an interesting rate sneaking up on us.
00:43:00
So if you're interested or inclined, you know, we'd love for those to weigh in on this with USDOT.
00:43:10
Next slide.
00:43:13
Thriving Communities Initiatives, I don't know how much you've all heard about this.
00:43:17
This is really a program that's been driven internally to USDOT.
00:43:24
They provide resources for technical assistance in the city building to foster thriving communities.
00:43:34
USDOT has a website dedicated to this program.
00:43:37
Again, you see the acronym Housing and Urban Development, again,
00:43:44
A link between housing and transportation infrastructure.
00:43:49
HUD was awarded $5 million in the last appropriations for 22.
00:43:55
USDOT received $25 million.
00:44:00
Congress, or I should say the House, has included an additional $100 million for FY 23.
00:44:08
We expect a notice of funding opportunity in the fall.
00:44:12
If that is the case, then it would probably only apply to that 25 million at USDOT and the five to HUD because I don't see Congress finishing their appropriations before the fall.
00:44:25
Maybe they'll surprise me and be wrong and surprise a lot of people, but I don't think they're going to hit that target.
00:44:33
Next slide.
00:44:35
Speaking of appropriations,
00:44:37
um the house is actually moving pretty well given the historical
00:44:42
I think the last time Congress passed all 12 bills signed by the President was back when my son was born, and I was still on Capitol Hill in 2004.
00:44:51
So it's been a long time, but the House did pass a minibus.
00:44:57
You've heard the omnibus term.
00:44:58
This is a minibus.
00:44:59
You've probably heard that before.
00:45:00
It packaged six bills together, including the Transportation, Housing, and Urban Development Appropriations Bill.
00:45:08
They did pass that last week, I think July 22nd.
00:45:12
It's consistent with the IIJA funding levels in terms of trust fund obligations.
00:45:19
They actually did increase some general fund spending for the capital investment grant program at FTA, a little bit more for Amtrak.
00:45:28
And of course, they've done earmarks again.
00:45:30
So this is two years in a row, I think it's two years, where they've included earmarks.
00:45:36
And there's earmarks for highways, for transit, as well as aviation.
00:45:42
We did a summary, not of the entire bill, but kind of the overarching pieces of the bill.
00:45:49
And I think we do now have a link bill to the committee report that lists all of the earmarks that are in the THUD bill.
00:45:59
So if that's something that interests you, it's on our website.
00:46:03
And of course you can always go to congress.gov and pull up the report that accompanies the appropriations bill.
00:46:10
Senate's a little bit further behind.
00:46:12
They haven't passed anything yet.
00:46:14
They continue to negotiate, which takes us to a CR, continuing resolution.
00:46:22
We're used to those.
00:46:23
They're frustrating.
00:46:24
It's tough to plan.
00:46:26
It's tough to execute projects when you don't know what you're going to have for the year.
00:46:29
I hate to say people are getting used to it, but
00:46:34
We're getting used to it and I don't know how long this next CR is going to be as you know the current fiscal year does expire at the end of September.
00:46:45
A CR, by its nature, can use funding at the current year's levels.
00:46:52
So for most programs, you're going to get 22 levels for however long the CR lasts.
00:46:58
After a two-day CR, you're going to get a prorated share for 60 days of whatever was spent in 2022.
00:47:06
So you'll get an obligation limitation, for instance, on highway trust fund set for 60 days prorated at the 2022 levels.
00:47:14
And as I mentioned earlier, advanced appropriations are not impacted by a CR.
00:47:25
because again, unique, I think, I've never seen it done, but the IIJA and putting that, I think it was 36 billion every year in advanced appropriations, it was essentially an appropriations bill within an authorization bill.
00:47:41
And USDOT has access to those funds short of Congress legislating them away.
00:47:47
So for some of those programs I mentioned earlier that are funded 100% or partially even,
00:47:54
by the advanced appropriations, USDOT should be able to move forward with those funds as they wait for Congress to finish up the trust-funded programs.
00:48:04
Next slide.
00:48:06
This is just a snapshot of what the House did.
00:48:07
This is not what's coming out.
00:48:09
This is not final.
00:48:11
I should probably mark this better.
00:48:13
This is just what the House did, okay?
00:48:18
You'll see the IIJA is between 21 and 22.
00:48:24
The blue is the contract authority from the trust fund.
00:48:27
The green is that $36, $37 billion in advanced appropriations.
00:48:34
And the orange or rust or whatever we're calling that is the general fund appropriations that the appropriations committees add annually to fund programs that are not trust funded.
00:48:48
As you can see, it's just a small bump.
00:48:52
But like I said, the large increases was, and it always is, when I was on the Hill for safety loo, you get the biggest bump in the first year and then you get
00:49:04
Maybe inflationary growth in the out years.
00:49:07
Next slide.
00:49:10
So the remainder of 2022, we've been doing a little bit of homework on the American Rescue Plan Act funds.
00:49:21
There were two tranches, if you will, of funding that went out to the states and then there was the local funding.
00:49:27
And there was an effort particularly by Senator John Cornyn and a lot of the local associations here in town to implement some more flexibility in how those funds can be used for infrastructure.
00:49:44
And Senator Cornyn had a bill that did pass the Senate, but it hasn't gone anywhere in the House that would have
00:49:54
included a cap, either the greater of 10 million or 30% of the funds received that could be used for new purposes, including transportation.
00:50:03
But like I said, that never passed the House.
00:50:08
We talked with the National Association of Counties not too long ago about what the final Treasury rule said.
00:50:19
And NACo felt very comfortable
00:50:25
in indicating that the final rule that was done by Treasury, which was back in January, actually addressed the 10 million piece of the Cornyn bill, but it linked to lost revenue that could be used beyond what the
00:50:45
What the ARPA bill specifically designated.
00:50:48
So Treasury Rule is on the Treasury website.
00:50:55
I don't know if this is impacting folks on this call.
00:51:01
You still have to justify to Treasury the use of funds.
00:51:06
But we thought it was at least something to make people aware of.
00:51:12
And if there's any questions, we can try to work offline if someone has additional questions or issues.
00:51:19
Next slide.
00:51:21
We've got elections.
00:51:23
Obviously, everybody knows that.
00:51:26
This is just, again, a graphic of what's out there, what the current representation is in the House.
00:51:35
As you know, they're all up.
00:51:40
The Senate, a third of it's up.
00:51:43
The Republicans have more seats to defend.
00:51:46
You know, everybody becomes a political prognosticator inside the beltway.
00:51:54
And because Virginia is so close, I'm sure a lot of that in Virginia, but we don't know what's going to happen.
00:52:01
A lot of the political analysis leans towards the House flipping to Republican.
00:52:08
Republicans in the Senate have more seats to defend.
00:52:11
But it could happen there as well.
00:52:15
I'm not going to pick.
00:52:17
The Cook Political Report says the Senate seats fives or toss ups, 19 favorite Republicans, 11 favorite Ds, Democrats.
00:52:26
Obviously this could change.
00:52:27
I wrote these slides on a week ago.
00:52:32
But it's always helpful, I think, that we at least are recognizing and paying attention to these things.
00:52:38
Next slide.
00:52:41
Outcome scenarios, I think these are obvious to folks.
00:52:48
The Republicans take the House and the Senate.
00:52:49
There's going to be more oversight and scrutiny of the implementation of the surface bill and the broader implementation of the IIJA.
00:52:59
Could Republicans cut spending?
00:53:00
Of course they could.
00:53:02
They have to do with legislation.
00:53:06
But I don't think the President is going to sign a bill that cuts spending.
00:53:11
for a bill that was just passed a year ago.
00:53:13
At least I don't believe they would.
00:53:18
But again, Congress is in the Congress and they can write whatever legislation they want and do their best to try to get it signed into law.
00:53:25
If there's a split Congress, in other words, one chambers R, one chambers D, again, you're going to continue to have more oversight.
00:53:31
But as long as the White House is in Democratic hands right now, I think at least for the next couple of years, the IIJ funding is going to be relatively safe.
00:53:42
I never say 100% here in DC, because it comes back to bite you sometimes.
00:53:47
But I'm pretty confident that the money will be available.
00:53:56
Congress is going to be looking to make sure that it gets spent and it's invested and people are put to work.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:54:04
Next slide.
SPEAKER_05
00:54:08
That's it.
00:54:09
Did I go over?
SPEAKER_00
00:54:13
Probably.
00:54:16
Great.
00:54:16
Well, thanks, Lev.
00:54:18
There's our contact information.
00:54:20
I know we threw a lot of information at you in a short period of time.
00:54:24
Please, if you have any questions, we have a couple of minutes now, I think.
00:54:27
If not, then please feel free to contact us at any time.
00:54:29
As Lev said, we're happy to follow up offline on anything that we covered.
00:54:34
And I will make sure that a copy of these slides get passed around and they're available following this meeting.
Lloyd Snook
Vice-Chair, MPO Policy Board
00:54:43
Good.
00:54:44
Thank you very much.
00:54:46
Questions now?
SPEAKER_07
00:54:46
Quick question for you.
00:54:47
You mentioned way back in your earlier slide about bridge funding and are new bridges available for any of that supplemental, coming down local batches and things, or is this only remediation for existing bridges?
SPEAKER_05
00:55:03
That's a great question.
00:55:04
I think it's just for existing.
00:55:09
So, you know, you could replace a bridge, but it would essentially be a new bridge.
00:55:13
What are you talking about?
00:55:15
A bridge that's not in existence at this point and building a brand new one.
SPEAKER_07
00:55:20
Yes, it's been in the plans since 1992, but it hasn't been in structure.
SPEAKER_05
00:55:24
You know, I don't, wow, that's a great question.
00:55:27
And it seems like a very obvious, I got to dig into that.
00:55:29
Don't take my word for it yet.
00:55:30
Let me, let's get back to you on that.
00:55:32
That's a great question.
SPEAKER_10
00:55:35
No, it's gotta be new.
SPEAKER_05
00:55:37
I'll double check that.
SPEAKER_10
00:55:40
Thank you.
Brian Pinkston
Member, MPO Policy Board
00:55:41
So this is really just a question for the group as well because I'm new to all of this.
00:55:49
So for instance, the bridges that are on the 250 bypass, Locust Park, those bridges, is that something that
00:56:00
How would this normally be funded to be replaced?
00:56:03
Or is it pretty dangerous, frankly?
00:56:06
I have to pull on every day to compare.
00:56:10
Would this sort of money be the best way to approach that?
00:56:14
Or is it something that's already part of VDOT's normal programming to replace?
00:56:19
Or is it only when there's sort of
SPEAKER_05
00:56:22
I would first contact VDOT and find out what their bridge program is.
00:56:33
But yeah, I mean, they've got bridge formula money right now that can be used for that.
00:56:38
They've got a grant program, new grant program that can be used for that.
00:56:42
I mean, generally speaking, I would assume that a state would either use its NHPP money or its surface transportation block grant funds.
00:56:50
Congress, in fact, has addressed the bridge issue
00:56:54
I think at least for the last two or three years by putting supplemental bridge money in the appropriations bill.
00:57:04
So there's a lot of funding that is available for bridges, but I can't tell you exactly how Virginia is doing it, but I wouldn't be surprised if it was a mix.
Brian Pinkston
Member, MPO Policy Board
00:57:17
Yes, I guess just to the VDOT folks here, I mean, how would that,
00:57:21
That bridge seems like it's in good enough repair but it obviously was designed in a time and place when
00:57:42
both site conditions now are not safe when you pull up you can't see the way and you try to get down you have to frame your neck like that i don't know it's even through a lot lower back then or whatever and i'm not willing to go with the design of those bridges right now but is that the sort of thing that could be a funding with these monies and if so how would that that need to be generated by requests from the city or um as i recall there's already on
Lloyd Snook
Vice-Chair, MPO Policy Board
00:58:11
on somebody's budget plan for the next few years to replace the bridge at Dairy Road.
SPEAKER_09
00:58:20
I assume there's some regular schedule for that kind of thing.
00:58:26
Yeah, well, bridge maintenance money, a lot of us, you know, the city does inspections on a bridge, I'm sure Brenda can speak more,
00:58:35
On a biannual basis, I believe you all do, and right now the city has actually repaired most of the bridges or will be repairing much of the bridges that have been raided poorly.
00:58:51
We've got four bridge projects currently under construction that have been funded.
00:58:54
along with Bypass and Melbourn High School was just recently replaced.
00:59:01
And the city received funding last year for the Dairy Road Bridge.
00:59:04
And my understanding, if I'm wrong, after those projects, all bridges in the city will have been upgraded.
00:59:12
And then recently- All of them had issues.
00:59:16
That had structural issues.
00:59:18
I mean, I know that Locust Place rebuilt a lot of
00:59:22
Well, it was 15 years ago?
Brian Pinkston
Member, MPO Policy Board
00:59:24
Yeah, it was one of those, it was updated and replaced with the original design.
00:59:31
Okay.
00:59:32
There's two different questions I think that were aggressive.
00:59:35
Like you said, the overall design of the bridge and the location and geometry is different than the, you know, the actual structural interior of the bridge.
00:59:46
Right.
00:59:47
So I don't know if it would be wasteful, but if this is,
00:59:50
If someone wants to invest in one or all safe purchase, then I'm going to keep going for two minutes.
SPEAKER_10
01:00:03
Other questions, comments?
01:00:07
One more.
01:00:07
Yes.
SPEAKER_07
01:00:07
This may be completely outside your portfolio, but you're talking about trucking and efficiency.
01:00:14
Have you heard any rubblings about more legislation to
01:00:19
increase the size of trucks, weight, length, etc.
01:00:23
That's been a 15-year anti-campaign for me, and I just want to make sure I'm not missing something.
SPEAKER_05
01:00:29
Well, I'd have to take a look at what the House bill includes right now.
01:00:34
As you know, the country didn't make patchwork
01:00:39
of weights and lengths in the various states.
01:00:43
I know there is an interstate regulation, but the Congress has in the past made exceptions for a variety of different industries sometimes, or if a state
01:01:01
wants to increase its weight for a particular reason.
01:01:06
So I think that it would be something that you need to look at in the appropriations bills individually, little legislative provisions, but I don't know.
01:01:18
I don't think there's any legislation more broadly
01:01:22
that increase or change the current statutes on that.
01:01:28
It tends to be more cut and bite changes per states or industries.
SPEAKER_07
01:01:34
All we're worried about is the federal overriding our state limits.
01:01:38
So for our little country roads where we can't handle the 90 foot length and stuff like that of roads that go like this.
01:01:50
Thank you.
SPEAKER_10
01:01:52
Anybody else?
01:01:52
I guess that's it.
01:01:55
Thank you so much to Ms. Royajan and Mr. Caruso.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:02:03
And I guess we're done with you all.
01:02:07
We'll move on to our next item on the agenda.
01:02:10
Okay.
01:02:10
Thank you very much.
01:02:11
Have a good evening.
01:02:12
Thank you.
01:02:14
So, Ms. Jacobs, Long Range Transportation Plan 2015.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:02:19
We have previously brought to y'all detention that we would like to issue an RFP to get consultant support for the long-range transportation project.
01:02:26
We met with some of you all individually.
01:02:28
We walked through it.
01:02:29
We met with some of you all for two.
01:02:32
Basically, since we have some passive rollover funding from FY21 and some active rollover funding from FY22 that we do not believe is a sustainable source in order to be able to staff up, we'd like to use a consultant to help support that process, especially since the team
01:02:48
Here at the PDC, it'll be the first time that this particular team of planners together and staff will do a long-range transportation plan.
01:02:56
So the scope was included in your packet.
01:02:59
The MPO technical committee suggested two minor edits, which we wanted to bring to your attention just because it will be what we would issue.
01:03:08
One of them is the date should say the end of the regional transit vision plan should say 2022.
01:03:12
It inadvertently said 2023.
01:03:14
We were thinking in fiscal year, so we'll change that.
01:03:17
The second one is we would like to add a bullet now that the regional governance study has been approved for funding.
01:03:24
We want to make sure that's a part of the background information.
01:03:27
And then we would like to add some language to state that we're really looking for proposals that would bring some new approaches and some creativity to the process.
01:03:35
And so we can use that to help evaluate proposals that we're receiving.
01:03:40
So those are the three suggestions that MPO Tech recommended adding to this book.
SPEAKER_10
01:03:47
So, do they have questions?
Lloyd Snook
Vice-Chair, MPO Policy Board
01:03:51
Do you require anything from us?
01:03:53
Yes.
01:03:53
A vote of approval?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:03:54
Yes, we would actually like to recommend a motion to approve issuing the RFP out of consultant support.
SPEAKER_10
01:04:01
And that's this document here, that's what it's about?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:04:04
Yes, the draft RFP.
01:04:05
Is that what it says on the back?
Lloyd Snook
Vice-Chair, MPO Policy Board
01:04:08
The page of the page 13 that
01:04:13
It begins on page 9.
SPEAKER_10
01:04:16
Yeah, 9 is for T. Yep.
01:04:21
If there's a couple changes that you'd suggest.
01:04:25
So do we have a motion on that?
01:04:28
Or questions or comments or criticisms?
SPEAKER_07
01:04:34
Questions.
01:04:36
Yes.
01:04:37
Olcro here.
01:04:38
There are so many benefits to
01:04:41
gathering people in meetings, and the more we're doing things only by surveying, the bigger the disaster result.
01:04:49
So I just want to make sure that there is enough or adequate routing in where we have been, because I was in multiple meetings over the last one, where through social media, all the dot lists was completely manipulated, because 300 people were told to show up and put their green dots on a certain
01:05:11
So I just am concerned when things like that tend to spew a whole flame off the rails.
01:05:25
So I want to make sure that we're sort of being above what we're at.
01:05:31
Innovation is great, but we have obligations to make sure that we're not messing up.
01:05:37
And that's, I think, what we're looking for.
SPEAKER_10
01:05:40
Thank you.
Brian Pinkston
Member, MPO Policy Board
01:05:42
Anybody else?
SPEAKER_10
01:05:48
Questions, comments, or motions?
Brian Pinkston
Member, MPO Policy Board
01:05:51
I will move that the RFP as previously before the amendments that have been before this afternoon indicate a move that we make the amendments and then just go forward.
SPEAKER_10
01:06:08
I'll second that.
01:06:10
Discussion?
01:06:10
All those?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:06:17
Motion carries.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:06:24
Okay, so then the next item also related to that is the appointment of the technical working group.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:06:36
Okay, the memo that was included in your packet was a staff recommendation for creating a technical working group for the LRTP with a suggested group of core and supplemental members.
01:06:48
Before I get too far into the details of that memo, there were several recommendations coming out of both CTAC and MPO Tech that I would like to share with you because it may change the direction of the conversation a little bit.
01:07:02
So I am going to share my screen to share with you
01:07:05
Those recommendations, and I apologize that they're not in the packet, but they were received yesterday and last week, so we couldn't leave it in.
01:07:15
Can you all see my screen online?
01:07:18
I'm getting into presentation mode.
01:07:21
We'll take a second to kick in here.
01:07:23
Okay.
01:07:24
At the CTAC meeting, what they recommended was no change to the core group as recommended.
01:07:28
The core group within the
01:07:31
memo that staff presented included the majority of MPO tech members as well as including an additional one or two members.
01:07:39
It also recommended a supplemental group.
01:07:42
CTAC did not suggest any changes to the core group, but they suggested adding the following to the supplemental group, both Albemarle and City Office of Diversity, Equity, and Inclusion, City and County School Board members, City and County bike head planners,
01:08:00
City Regional Chamber of Commerce, Charlottesville Regional Chamber of Commerce, excuse me, and University Transit Service.
01:08:07
Those were the recommendations of CTAC.
01:08:11
When we got into the MPO technical committee meeting, there was a really robust discussion that I thought was really valuable about duplication between MPO technical committee and what it's charged to do and creating a separate LRTP technical committee.
01:08:26
And so the discussion really formed into
01:08:29
Their recommendation was that MPO Tech remain the technical committee for the long range transportation plan.
01:08:36
In order to not take their entire meetings for that, they agreed, the committee proposed that they would still continue to meet every other month, meeting on the off months as needed.
01:08:47
And in the off months, inviting the supplemental recommended group to join so that we could get comprehensive feedback from those other stakeholders.
01:08:56
but not necessarily derail MPO tech business that needed to occur.
01:09:01
So the recommendation there was to keep the MPO technical committee as the core LRTP technical committee so that there is not a new committee formed and duplication on that and then have a supplemental group made up of the staff listed here.
01:09:17
One note that is different is MPO tech did not recommend separate
01:09:24
It was white head planners.
01:09:27
They said that a city and a county planner would be able to serve the role as the city and county planner and we don't need multiple planners.
01:09:34
They also recommended that rather than a school board member, it might be more appropriate for it to be city and county school staff.
01:09:41
Somebody in charge of director of transportation that can speak more perhaps than a board member could.
01:09:46
So those are the changes and they also included adding UTS
01:09:53
I don't think that's on that list, but they agreed with the recommendation of CTAC to put UTS on the supplemental.
01:10:00
So I wanted to bring all of those recommendations up because it may change how you all have a discussion over whether you guys would agree that MPO Tech can serve as that technical committee with the changes that are recommended by either CTAC or MPO Tech or a combination of the two.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:10:18
I guess the question I've got is you started off with a recommendation
01:10:22
for a core group of, what was the original size, like 12 members or something, one, two, three, four, five, 11 people, and then six supplemental, and we're talking about adding about 20 supplemental people.
01:10:42
That changes the nature of the supplemental group drastically.
01:10:48
Why?
01:10:49
Isn't it at some point having 20 and some in there not much better than having three or four?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:11:00
I think the distinction with the supplemental group is we would not necessarily use that group as a push up your sleeves, get into the weeds work group.
01:11:10
It would be to make sure that we are sharing the information with these key stakeholders and receiving feedback from those key stakeholders.
01:11:19
So there would only be a meeting call if there were particular bulleted topics that needed to be discussed to get feedback from this broader coalition of people that are transit tangential, not necessarily direct transit or transportation.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:11:36
So if the core room is
01:11:40
MPOTEC.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:11:49
I think it would be more than a mailing list, but I do take your point.
01:11:53
I think what it would not be is a group of 30 people expected to workshop details of the plan because that would be on the plan.
01:12:08
So we'd love to get
01:12:10
policy boards, feedback on the recommended changes by CTAC and MPOTAC and see what you all would recommend or support.
Brian Pinkston
Member, MPO Policy Board
01:12:19
To be honest, I'm looking to you all's expertise on this.
01:12:23
This is a recommendation that you feel is obviously a bigger recommendation.
SPEAKER_10
01:12:28
I have a lot of confidence in
Brian Pinkston
Member, MPO Policy Board
01:12:32
I appreciate that.
01:12:35
We definitely felt
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:13:01
That was a really good collaborative process to get to where we are, you know, and really thinking through not just creating a committee for committee's sake, but what is the value and what are the right people to have on that committee?
01:13:12
So I think staff feels, feels favorable towards the recommendations that we got from, from those two.
SPEAKER_07
01:13:21
Yeah.
01:13:21
Okay, good.
01:13:22
I want to make sure I'm just not going to have a long time here.
01:13:27
I very much support the
01:13:28
Those are the experience doing the core stuff.
01:13:31
And if they're, I'm always in favor of smaller chunks being sent out to your supplemental responders and all of us.
01:13:39
Here's chapter one, then later here's chapter two, rather than the 55 page thing all at once.
01:13:44
My brain doesn't handle that very well.
01:13:46
So that way people will have different chapters or different elements will be of particular interest to the different supplemental people.
01:13:55
And they can weigh in on that if that's something that they
01:13:58
Just one particular question.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:14:13
What is the difference between what was suggested in the initial memo for city and county climate action versus city and county climate mitigation?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:14:26
I think that was just me typing the words without considering how important that might be, but it's really a climate-related staff member in the city and the county, probably to identify who the best person is in each, but I may not have titled that properly.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:14:42
What I'm curious about is, I guess, when you say add the following groups,
01:14:53
Let's not add the following people.
01:14:55
It's maybe adding the following.
01:14:58
Again, it doesn't really matter.
01:14:59
I suppose if
01:15:00
If the purpose of it is to simply increase the number of people who are being exposed to the workflow from comment at appropriate times, I've sort of had this vision of trying to get this supplemental group to make some sort of a recommendation en masse, which may not be possible, or as opposed to having them make recommendations, for example, the Albemarle County folks,
01:15:28
on here might make the recommendation to the Albemarle County resident there, people who are on the court committee and city, likewise.
01:15:35
I'm just trying to visualize how it's going to work in progress and process, and I trust that you all have enough sense to keep it from being a complete disaster.
01:15:49
Because it seems you may have 30 people involved as decision makers.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:15:53
Yeah, and that is definitely not the intent is to have 30 decision makers.
01:15:57
It's to make sure that we're getting the critical feedback we need from all of these different areas so that we can then have MPO tech making recommendations to the policy board.
SPEAKER_07
01:16:11
I'm going to ask Kevin to follow up with me because I would assume that you will be in contact with all of your colleagues about all these other issues before you even come back to tech.
SPEAKER_10
01:16:23
Are you asking if we would be adding these other groups if we would talk to them ahead of time to make sure that they should be part of this?
SPEAKER_07
01:16:36
No, I'm talking about issue by issue.
01:16:38
So we know there's a land use and transportation connection, so you're going to not be saying, well, you're a land use person, I'm like, I'm sorry, but you're going to be having a collaborative discussion about all of that as you go along.
01:16:48
Excellent.
01:16:49
So I think we covered it as far as that, if there were items on the supplemental that were left out of that loop, that might be different.
01:16:57
And my second follow-up question is, what's the role of CTAC?
01:17:00
Because I was on that for eight years, and that's what we did, was to read the LRTB.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:17:04
So where are they going to be?
01:17:05
They will continue to meet as CTAC serving in the same role they did before, giving the citizens perspective.
SPEAKER_07
01:17:11
Hosting public meetings and that kind of thing.
01:17:13
That, I hope, will be able to get back to that, because it will seem bad.
01:17:16
What is CTAC?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:17:22
Citizen Transportation Advisory Committee.
01:17:24
It's a subcommittee of the NPO that is related to the citizens.
Brian Pinkston
Member, MPO Policy Board
01:17:29
How does that constitute the chairperson of that?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:17:34
The chairperson of CTAC is actually Lee Kondor who is here on here with us today.
SPEAKER_10
01:17:42
OK, so we have a motion on the floor.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:17:46
Is that right?
01:17:47
And second.
01:17:48
Are we ready for a vote?
01:17:51
All in favor, say aye.
01:17:52
Aye.
01:17:53
Aye.
01:17:54
All opposed?
01:17:56
OK, the motion carries.
01:17:58
Let's see.
01:18:00
Now we come to fiscal year 2021 to 2024 TIP.
01:18:05
Mr. Nichols?
SPEAKER_11
01:18:09
Yes, sir.
01:18:11
In your packet, you have a TI-3 amendment.
01:18:17
It is the Route 20 bridge replacement.
SPEAKER_10
01:18:21
I don't know if Mark and Sue are involved.
SPEAKER_11
01:18:26
Stacy Londrey has any more to add to this.
SPEAKER_10
01:18:31
But basically, this type of amendment will need to
01:18:37
This is what we would more closely know as the Belmont Bridge.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:18:53
What is the effect in general terms of this amendment?
SPEAKER_11
01:18:59
Yes sir, so basically I think it's adding about almost $7 million to the project.
Brian Pinkston
Member, MPO Policy Board
01:19:07
due to what sorts of problems.
SPEAKER_09
01:19:14
Yeah, I'm Mr. Snook.
01:19:16
So the Noam Bridge, the first major here, you can see it was this whole block of amendment.
01:19:22
I think if we were moving the project towards advertisement on a previous budget of $25 million, there was a need to increase it to 31.
01:19:37
And that's what you see on the first page.
01:19:38
And that's what happened back in, I know there's a date there someplace, but it was sometime last year.
01:19:45
And then after the project was actually bid,
01:19:48
The budget was 31 million.
01:19:51
It was insufficient because your bid that you received was 35.
01:19:55
VDOT in the meantime managed to provide $4.2 million to cover that differential.
01:20:00
And that's what you're seeing on the next page, as well as another $2.7 million that was found for the project.
01:20:09
It came about much later with the action of that project.
01:20:13
The demo money was made available.
01:20:15
So currently that was a 2.7 to put on the project.
01:20:19
The city elected, it has a pretty large cash contribution on that project.
01:20:27
So you made about $6 billion.
01:20:30
And that 2.7 could be used to sort of offset that 2.7.
01:20:34
But my understanding,
01:20:37
2.7 BUs also have that $6 million contribution.
01:20:42
But my understanding was the city elected to leave it there as extra funding, if you will, on that bridge in case we have cost overruns.
01:20:50
I think to get closer to the project solution that we haven't had in the cost overruns, then the city's contribution may be decreased by this additional $2.7 billion.
01:21:04
Which you'll see on that second page.
01:21:06
It's really going from 31 million to 38 million and that's 4.2 million together.
SPEAKER_04
01:21:17
And I'll just add to the demo funds are a type of federal funding that existed in a previous project and had to be repurposed.
01:21:28
It's an earmarked type of funding that was repurposed and there are certain parameters
01:21:33
Geographic parameters even that limit the number of projects that we can apply those to.
01:21:40
So that's how those funds came to be on the Belmont Bridge project.
01:21:45
It was one that was in construction.
01:21:46
We can spend those funds and it met all of the pretty strict eligibility criteria for that type of funding.
01:21:56
There's usually a timeframe restriction and like I said, a geographic restriction on how it can be repurposed.
01:22:04
So the action of the TIP amendment is simply to increase the estimate on the project to accept that new funding.
01:22:14
The TIP must match our state version of the TIP, which is called the STIP.
01:22:20
And that's what this amendment will do because of its value.
01:22:25
That's why it's coming before the board tonight for action.
SPEAKER_10
01:22:33
So we need to pass a motion to adopt that change to the fifth amendment.
SPEAKER_07
01:22:44
Well Stacy, keep an eye on where that money is because other communities would like to have forgiveness of their match too and the fact that this has gone from 10 million to 38 million in a decade makes my brain explode.
01:22:59
It's a zero sum as far as the money in the state is concerned.
01:23:01
So I'm very concerned that this multiplication happens.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:23:10
So with the bid at $35 million, is it the sense that this particular set of expenditures and reshuffling of things gets us to fund $35 million and we're ready to do it?
01:23:28
Or are we still looking for more money?
SPEAKER_09
01:23:30
I don't think you look for more money right now.
01:23:32
I mean, your destruction bid, you have about $35 million to take it.
01:23:38
So, $100,000, right?
01:23:40
And so, the project's fully funded and moving forward.
01:23:43
I don't think, to date, there's any significant cost that it runs.
01:23:47
I think there's still a bit of bubbles in the contingency period.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:23:55
I think staff would be looking for a motion to approve the proposed TIP amendments as delivered.
SPEAKER_10
01:24:04
Okay.
01:24:04
Is there such a motion?
01:24:06
I would move that the amended TIP that should be recommended by the commission that we approve it.
01:24:28
Do I have a second?
01:24:31
Second.
SPEAKER_10
01:24:34
Any discussion?
01:24:39
If not, are we ready to vote?
01:24:42
All in favor say aye.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:24:44
Aye.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:24:45
All opposed?
01:24:49
None.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:24:49
The motion carries.
01:24:52
The motion that was passed on the Technical Working Committee
01:24:58
I did not catch nor did Gretchen Thomas online catch who first or seconded that for the minutes.
01:25:04
I'm not sure I heard.
01:25:06
Okay, Brian Pinkston first and in a second.
01:25:12
Yeah.
01:25:13
Sorry to interrupt.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:25:13
Okay.
01:25:16
All right.
01:25:18
Staff updates.
01:25:21
First up is adjustments.
01:25:24
Yes, sir.
SPEAKER_11
01:25:26
There are three adjustments that you need to attend.
01:25:35
The categories are preventive maintenance for bridges.
01:25:41
That increases 16.4 million.
SPEAKER_10
01:25:46
Preventive maintenance and system preservation is 44.4 million.
01:25:56
Any questions on those?
01:26:06
Well, I guess the question is,
SPEAKER_07
01:26:21
And I personally have a really hard time keeping straight all these categories when there's no narrative to go with it to say, but I am concerned about reductions in the safety money because we have safety issues all over county roads that are causing repeated accidents and highway fatalities.
01:26:37
And so I really want to emphasize the importance of that from my perspective down here.
01:26:43
We've got to take great care to make sure that Apple funding is available to solve some of these things as well.
SPEAKER_10
01:26:53
Are there issues on this group's minutes?
Brian Pinkston
Member, MPO Policy Board
01:26:56
All right, just a question.
01:26:57
So, one for the bridge, is the amendment in the needs of our adjustments?
01:27:04
This is more of this sort of notification?
01:27:06
Yes.
SPEAKER_10
01:27:07
Okay.
01:27:12
Next, transit grants and RTP.
01:27:16
Shannon?
SPEAKER_07
01:27:17
Hi, everybody.
01:27:20
So we are still working on the Regional Transit Vision Plan during our final phase of public engagement.
01:27:28
Our survey is still out.
01:27:30
We extended the public engagement period a little bit further.
01:27:33
We've had several focus groups.
01:27:35
We've had a really good transit event where we got 50 surveys from transit riders.
01:27:40
We pretty much talked to everybody who was riding the bus that day.
01:27:43
We had a lot of staff there, including a Spanish interpreter who was able to collect Spanish surveys, which was awesome.
01:27:51
We also had a focus group that was in Spanish with those surveys as well.
01:27:58
We are looking at doing some more in-person events with Albemarle County's public engagement band.
01:28:05
And we are still meeting with, we're working with the housing group.
01:28:12
We've been presenting to different committees and reaching out to our stakeholders and working with them to get more surveys from their clientele.
01:28:22
So that is the vision plan.
01:28:25
Everybody, please take the survey and share that with your network.
01:28:29
And the governance study is starting this month.
01:28:33
And the governance study will be to help fund the projects that the vision study is identified.
01:28:43
And that will include the entire region.
01:28:48
It will be convening a advisory committee with representatives from the jurisdictions, including Albemarle and Charlottesville and the MPO.
01:28:59
and we'll be reaching out to those committee members soon.
01:29:04
And that's about it.
01:29:07
The RTP is not meeting in July.
01:29:09
They will be meeting in August and having another vision plan up to the end.
Brian Pinkston
Member, MPO Policy Board
01:29:18
Yes.
01:29:19
So you're not meeting tomorrow?
SPEAKER_07
01:29:20
We're not meeting tomorrow.
Brian Pinkston
Member, MPO Policy Board
01:29:23
Question?
01:29:24
I was curious on this.
SPEAKER_08
01:29:26
open houses and stuff you have, any anecdotal reactions that you're hearing?
SPEAKER_07
01:29:34
People are really excited about having weekend service.
01:29:37
A lot of people work on Sundays.
01:29:40
There's a lot of service workers who work on Sundays and late nights and they are not able to use public transit to get home or get to work and home on weekends.
01:29:53
So they were really excited about the
01:29:55
New services that were in the plan and getting more hours of service.
Brian Pinkston
Member, MPO Policy Board
01:30:03
We have a sense of that market for late-night different types of things, thousands of people, hundreds.
SPEAKER_07
01:30:17
The Latino focus group had about
01:30:22
My people in it and all of them talked about not being able to get home from work at night, having to walk in the dark on your 29, feeling really unsafe, being able to walk along that street.
01:30:39
So I would say that there's a pretty good market.
01:30:43
I mean, if you look at the people who are employed and who work in the service industry and have to
Brian Pinkston
Member, MPO Policy Board
01:30:50
We can talk later, late night, midnight, 1 a.m., that kind of thing?
SPEAKER_07
01:30:58
Yeah, I would say most restaurants probably put your antenna on there.
SPEAKER_10
01:31:03
Oh, okay.
01:31:05
We're talking in the meantime.
Brian Pinkston
Member, MPO Policy Board
01:31:08
Well, we saw that prior to you doing your study, that was one of the main things that your team asked of us.
01:31:15
It's just, it's a matter of having enough
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:31:19
I'd love to add to that, you know, our outreach and engagement focus has changed a little bit from not really trying to identify a target number of people hitting the survey, right?
01:31:35
Because we know, as Supervisor Malek said earlier, that's not always the best feedback, but it's really staff intensive time to go speak to people and to hear their feedback.
01:31:45
And I'm not trying to manage expectations, but that does mean across an eight hour day, you might get 20 or 30 versus being able to get hundreds to show.
01:31:54
But I feel very strongly that it's much more representative of our community and it's speaking to transit dependent riders and people who potentially would use transit if they could.
01:32:05
So I don't know at the end of this engagement if we're ever going to be pleased with
01:32:11
We're not pleased, but not feel like there should have or could have been more, but I am really pleased with the shift in doing much smaller and much more focused communications with people so that we can really hear what isn't coming up in questions on the survey.
SPEAKER_07
01:32:29
Has there been discussion with the outlier employers from Robert Jefferson and the War's Head on the opposite end?
01:32:36
Because those folks who worked the evening shift there
01:32:40
have been high and dry for a long, long time.
01:32:42
And whether they're being served now, I don't remember, but I know the board has discussed quite a bit over the last 15 years about getting transit out there to them.
01:32:50
In some fashion, whether we need to set it separately through John to pick up the people.
01:32:55
And also the other questions are, is there an opportunity to reach out to businesses who are not on a bus route and not possible for our transit to get to, but they should or could be encouraged
01:33:08
In some way, I mean maybe federal tax credits or something, I don't know, to be able to provide that van ride home for their staff when they get off shift.
01:33:17
I mean, it seems like it would be a reasonable incentive for a revenue source, enough people to fill a van, let's say, when you get 30 or whatever coming off at the same time.
01:33:27
I have seen people walking to the airport in the snow because there's no way to get there.
01:33:34
I've been trying for 30 years to get transit to here, so far, but I think that it is really grateful for the way you're approaching this now, because it's going to be hearing from the people who are willing to be taking it.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:33:49
So can you repeat the second recommendation?
01:33:51
You said Boar's Head and what was the other end?
SPEAKER_07
01:33:53
The Ronald Jefferson Pantops.
01:33:55
We had trouble getting service to the Veterans Clinic, getting the transit up to the middle, because these old guys can't walk up the hill.
01:34:03
I can't walk up the hill.
01:34:04
So that was a debate we had back in 2012.
01:34:12
So these are those ones that infringes.
01:34:14
I know there are limits to what's possible, but it would be great to know where those limits are now and where the gaps are in the meantime.
SPEAKER_10
01:34:24
Yeah.
SPEAKER_08
01:34:26
One thing that the region might consider and might want to track is RONA is launching an effort to do a statistically significant
01:34:34
Household Transportation Survey modeled after the Metropolitan Washington Council of Government's methodology.
01:34:41
This supplements the National Transportation Household Survey, which tends to be a little thin in some of our smaller communities like Charlottesville.
01:34:50
So that might be something for this region to consider and watch and do in future efforts.
01:34:55
It could be something that's
01:34:56
Statistically Significant Survey focused on how your community is using transportation systems because that data can influence things like your transit planning, but also as you go into an LRTD cycle, how your model is calibrated and how your model performs.
01:35:15
Having that localized data can really help you narrow in on something that's truly reflective of your community's behavior.
SPEAKER_07
01:35:23
Is that only possible at census intervals or is that something where we can do at our own initiative?
SPEAKER_08
01:35:31
You can do that as your own initiative.
01:35:33
There are models and methodologies out there.
01:35:36
There are, you know, resources available through different state and federal funding programs to do that, to gather that supplemental data.
01:35:47
You know, oftentimes you're probably looking at identifying a consultant for a research partner to conduct
01:35:53
You know, a survey doing in-person telephone, digital targeting in a way that's just statistically significant and kind of matches the mosaic of your community.
Brian Pinkston
Member, MPO Policy Board
01:36:06
It's a multi-prong approach.
01:36:08
Normally you start off with a mailing out to the household, so that's the easy and quick methodology.
SPEAKER_07
01:36:14
And well, of course, wonderful work with us for our community.
01:36:17
Special thanks.
Brian Pinkston
Member, MPO Policy Board
01:36:19
They're expensive.
SPEAKER_07
01:36:21
They are expensive.
01:36:22
But you get what you pay for it.
Brian Pinkston
Member, MPO Policy Board
01:36:24
We would need to probably apply for technical assistance to help offset that cost.
01:36:30
Correct.
01:36:31
So we'll just keep that in mind.
01:36:33
Pretty expensive.
SPEAKER_08
01:36:34
Yeah, but you might want to talk with your colleagues in Roanoke as they get rolling with that.
01:36:39
I'm sure they could share some lessons.
01:36:42
Okay.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:36:42
Yeah, we're done, Roanoke.
01:36:44
They also are
SPEAKER_10
01:36:45
In case there's nothing to remember you can go to another camera.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:36:52
We also, you know, besides the focus groups and the, you know, the one-on-one conversations, staff is going to be meeting actually this week to start trying to scour what types of community events are already going to be occurring that we can either table at or we can ask for the event we're at.
01:37:07
So if you guys know of anything or you'd recommend, hey, that's kind of a large gathering, you should be there to get more participation, please share that with us so that we can try to allocate staff time to get people in these different places as much as we can.
SPEAKER_07
01:37:22
You may have some CTAC volunteers who would like to pick up some slack on some of this.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:37:33
Okay, thank you.
01:37:34
Next is the ride share, Sara Pennington.
01:37:37
Sara, anything to share with us?
Sara Pennington
RideShare Program Manager
01:37:41
I'll keep this brief to keep us on schedule, but just a couple of quick things.
01:37:45
Obviously, we are
01:37:46
Working at closing out the FY22 fiscal year and beginning FY23.
01:37:52
We will be participating in two main initiatives with DRPT and the state's CAPS programs, which stands for Commuter Assistance Program.
01:38:06
There will be Discover Transit Month in September and then Rideshare Month in October.
01:38:11
So we are just waiting for more information from the state for how we will proceed in promoting those.
01:38:18
So stay tuned, there will be lots more information.
01:38:21
And then the other quick thing I wanted to update everyone on is the Afton Express.
01:38:26
It is closing in on its one-year anniversary, which will be September 1st, which is really exciting that we've made it through, almost made it through the year.
01:38:36
I'm sure there will be more information about that celebration as well to follow.
01:38:40
But number wise, we've been really impressed with the ridership data.
01:38:45
I have not seen the full data for the month of June, but I was told that we had more than one day where we had over 50 passengers.
01:38:54
which is about the highest that we've seen.
01:38:56
I can say that in the month of May, the average was 36 passengers and the total number of rides even including the holiday was around 758.
01:39:08
In addition to celebrating the success of the program, they will also be adding a fourth route.
01:39:18
They received funding from
01:39:20
The State and the Commonwealth Transportation Board to add a fourth route.
01:39:25
They're right now in the process of procuring a bus and then, of course, hiring some drivers, but that route most likely will be focusing on those 12-hour shifts at the health care system.
SPEAKER_10
01:39:39
Thank you.
SPEAKER_07
01:39:41
Smart to bail.
01:39:44
Kevin, remind me, please, where we are on the Parti thing on Patterson Mill.
01:39:49
Did that get funded?
01:39:51
That right, pardon, right?
SPEAKER_10
01:39:53
Yes, that was funded.
01:39:54
Okay, so.
01:39:55
On interest for SCALE, but it's not, the funding has not come about quite yet.
01:40:01
We still have a few more years since the delay for SCALE is, but it is fully funded in a six-year plan.
SPEAKER_07
01:40:06
Great, so as soon as that's ready, then they have to express and stop there and pick up a whole bunch of conversations and fill the class with them.
01:40:12
And that will be good.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:40:14
Thank you.
01:40:14
Okay.
01:40:15
I'm trying to push things along here because I actually have to be someplace else at 6 o'clock.
01:40:21
So, Brian?
SPEAKER_11
01:40:22
Yes, so basically the NDO is including the final application process for the SMART SCALE project.
01:40:31
We do have the city, the county's resolution.
01:40:36
We are going to get the students hoping around August 1, I think will be interesting.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:40:44
So if it would be on the agenda for the Council meeting on August 1st, is that the notion?
SPEAKER_10
01:40:51
Yes, it was definitely scheduled for August 1st.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:40:55
Okay, I'll make a note to make sure of that.
Brian Pinkston
Member, MPO Policy Board
01:40:57
Does that mean we sort of approve the whole slate, or just the two that are Charles-related?
SPEAKER_11
01:41:07
On the council agenda, there will be four in-scale projects, which will be District Avenue, 5th Street, and the ones that are in DO.
01:41:27
Can I ask a question or not, somebody, real quick?
Brian Pinkston
Member, MPO Policy Board
01:41:32
I'm assuming this is like an update as well?
SPEAKER_11
01:41:34
Well, and I should say this too, the sketches that were provided in your packet, they're just preliminary.
01:41:42
I'm sure they are something to change.
01:41:43
So the way I'm doing that is finalizing those sketches as well.
Brian Pinkston
Member, MPO Policy Board
01:41:48
I'll be brief.
01:41:49
So the one that's over by
01:41:55
So the decision was made to capture one of the residents there so that people coming up the meadows can go west as well as east, is that right?
01:42:22
Is that what I'm seeing here?
SPEAKER_09
01:42:23
Yeah, what was happening with that was, there's actually two houses there, the first two houses was blocked.
01:42:28
And the first one was pretty much impacted, regardless.
01:42:32
The second one was the grading was happening, even, I think as I recall, when we were talking about the design, they just made it, you know, outbound, not really inbound, kind of still, but the impact should be willing to be pushed over and onto that property.
01:42:47
I think that our intent is to try them.
01:42:49
And the note right there is the grading will likely impact the majority of the property,
01:42:53
to achieve the acceptable approach coming in there.
01:42:58
But we're, I think, hopeful that at one point maybe the property itself might be redeveloped at one point in the future.
Brian Pinkston
Member, MPO Policy Board
01:43:05
Okay, because the first time I saw this, I don't remember how many months ago it was, there was only an eastbound exit.
01:43:13
And now you can go both east and west.
SPEAKER_09
01:43:22
That was a reflection of your comments.
01:43:24
Your election has been, you know, down the hill.
Brian Pinkston
Member, MPO Policy Board
01:43:36
You say things sometimes and you're not sure what happened.
01:43:40
I like what I see.
01:43:43
And then the other thing was over at hydraulic and Whole Foods.
01:43:52
So I'm not sure if there's any news outside of this meeting, Michael, but got a whole bunch of feedback from Nicky about how his or that trail system should try to intersect with this project and that I guess if you make some certain improvements in sidewalk sizes or curb cuts or whatever, then that would simplify that.
01:44:17
We might not do part of the overall trail system as part of this project.
SPEAKER_09
01:44:22
I think what Ned's trying to pose is that the current plan shows, and it's primarily a work with the roundabout, the main purpose of the plan, and the plan did towards the end extend the shared use path that the city built
01:44:50
A long bypass that terminated before you got to that drawing.
01:44:54
The extended that shared use path down to Brandywine.
01:44:57
And I think that what Mickey's asking is that why not continue that on up to the next street, Mickey Drive.
01:45:03
And a couple of different hurdles or challenges to doing that.
01:45:08
One of them was, you know, this was funded to a smart scale project several years ago.
01:45:12
It wasn't part of the scope.
01:45:15
One of the emails I just recently saw was like, you know, you start adding something to the scope afterwards,
01:45:20
How does that get paid for?
01:45:21
Is that some kind of locality or somebody else wants to pay for it?
01:45:25
So I put that in, you know, that one aspect for your consideration.
01:45:31
And the second one is the technical.
01:45:33
How do you get it done?
01:45:34
How do you get it accomplished?
01:45:36
And part of that property is three sections along there that might pose issues to extending it.
01:45:42
The first is that City Parkland right there, that's the former brandy one and hydraulics are small, but you know,
01:45:50
And the second is that the culvert that is going under hydraulic might have to be extended.
01:45:57
And if that was the case, that might be very expensive.
01:46:00
And the third potentially most challenging is the Region 10 building that's there is pretty close to the street.
01:46:09
And so trying to put that in there and still meet some separation of shared use path to hydraulic might cause some impacts to that building.
01:46:18
Those have not been assessed and the project is really not that was outside the scope of the original project and so funding for it might be an issue so maybe if it's an issue that the city really wants to push then maybe we should be talking about this area and I'm coming to this right now you know I just followed her in the meeting about the funding so it's something that the city is interested in pursuing interested in maybe putting some money towards
01:46:46
And maybe we can come back and sort of really assess how those impacts to the properties of the culvert could or could not be accepted.
01:46:53
But last point I would say is we're going to a design-build process.
01:46:57
We've held a public hearing.
01:46:59
This is how it's coming after the public hearing.
01:47:01
And we're really trying to ramp up the traffic without our RFP.
01:47:04
So if it's something the city is serious about, I think we would need to move with some speed.
01:47:10
Okay, thank you.
01:47:12
Okay.
SPEAKER_10
01:47:14
Next, we've got roundtable updates.
01:47:17
Are there any roundtable updates?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:47:19
I'll share an update that the Director of Transportation, Planning, and TJPDC will be returning very soon.
01:47:25
You can tell I'm very excited to share that, and she will be with us at our next round of meetings.
01:47:30
Great.
SPEAKER_07
01:47:31
Give her our best, please.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:47:34
She actually came in today with the meeting.
01:47:36
We're very excited to see her.
SPEAKER_08
01:47:40
Any other updates?
01:47:41
I'll give a quick update for DRPT.
01:47:44
Just a reminder that we have a post-award grantee webinar tomorrow, so anybody that's received DRPT grant awards, please make sure you attend.
01:47:53
These are good meetings.
01:47:54
We present a lot of information regarding grant requirements and things like that.
01:48:00
Everybody should receive multiple email reminders with the links to sign up.
01:48:04
Thank you.
SPEAKER_11
01:48:06
The only one I would say for CAT is we require a state statute to
01:48:10
TSP, we will be starting our process.
01:48:14
We will be using the state's bench contracts to get a contractor from onboard probably in the next 34 time values.
01:48:24
It's probably about a 14-month process.
01:48:27
We will make sure we are done sometime back in December of 23.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:48:32
And for the minutes, TSP is?
01:48:35
Transportation.
SPEAKER_10
01:48:37
Strategic plan.
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:48:38
All right.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:48:40
Items, we didn't add anything to the agenda, so we'll skip that.
01:48:50
Matters from the public, is there any public who would like to address us?
Christine Jacobs
Non-Voting Member, MPO Policy Board
01:48:55
If you would please use the Zoom feature, raise your hand.
SPEAKER_10
01:49:02
Okay, no matters from the public.
Lloyd Snook
Vice-Chair, MPO Policy Board
01:49:05
Well that lets us adjourn then, ten minutes early.
SPEAKER_10
01:49:12
Thank you so much.